Site Name: Tata Steel Scunthorpe

Location: Central Power Station (CPS)

Client: Project &Technology department

Programme: 10 weeks

Scope: To install supports and 1000mm diameter gas main x approx. 300mtrs

Client Requirements
Zone 5 was a payback scheme.  It allows us to use our power station as additional consumer for a particular type of gas, which allows us greater flexibility in how we operate.

Our Solution

  1. To supply materials, fabrication of 1000mm diameter pipework including lobster back bends, support steelwork including trestles, gantry’s and access staircases.
  2. To provide Site management, supervisors, tradesman, scaffold access, craneage, plant tools and equipment to carry out the installation of 1000mm pipework, support steelwork including trestles, gantry’s and access stairways.

Results

  1. Safe and satisfactory completion on time to ensure all tie ins to existing gas mains occurred during a 36 hour planned stoppage during Tata steels annual plant stop.